The costs nobody puts in the quote

Cost overrun is the thing homeowners regret most, and the commonest cause of a fight with a builder is not late payment but work nobody agreed to in writing. Both come from the same place: a scope that was never written down properly and a budget that only counted the build.

Pick what you are doing. This gives you a range, the costs that sit outside a builder's quote, and a written scope you can send to three of them so the answers come back comparable. Nothing is uploaded and it runs in your browser.

What are you doing?
Pick everything that applies. Some of these trigger costs you may not have thought about.
Rooms
Services
Fabric
Finishes
Structural
Outside
Roughly the national baseline.
Asbestos is very likely. Artex ceilings, garage roofs and floor tiles are the usual places.
The finishes move the number more than anything else.
£34,650 to £66,900
Everything, including the costs outside the builder's quote
£26,500 to £46,000
The building work itself
£8,150 to £20,900
Everything else
The gap between those two figures is the point of this. A builder quotes the middle number. The one that leaves your account is the first one, and the difference is typically 31 to 45 per cent on top.
The work itself
Kitchen
Supply and fit. A layout change costs considerably more than a swap, because the services move with it.
£12,000 to £20,000
Family bathroom
Full strip out and replace. Moving the soil pipe is the expensive decision.
£8,000 to £15,000
Full rewire
Three bed house, new consumer unit, Part P certified. Needs replastering after, which is often quoted separately.
£6,500 to £11,000
What is not in the builder's quote

These are the ones people find out about later. Not every one will apply to you, but each is triggered by something you have picked or by the age of the property.

VAT20 to 20%, so £5,300 to £9,200Almost always
A quote from a VAT registered builder may be shown excluding VAT. On a £60,000 job that is £12,000 you had not counted. Ask explicitly whether the figure includes it. Some work on properties empty for over two years qualifies for 5 per cent, and a new build is zero rated, but a normal renovation is not.
Contingency10 to 20%, so £2,650 to £9,200Always
Ten per cent on a modern house, closer to twenty on anything pre-1960. Joists, wiring, damp and drainage are the usual surprises. A project without a contingency line is a project that will go over, because the contingency is not optional, only the planning for it is.
Asbestos survey and removal£200 to £2,500Properties built before 2000
A survey is a few hundred. Removal is licensed work and costs considerably more. Artex ceilings, garage roofs and old floor tiles are the usual finds.
Everything that goes in it afterwards£0 to £0Always
Blinds, curtains, light fittings, furniture, white goods. The build ends and the spending does not. This is regularly a five figure sum that nobody planned for.
Your contingency should be 15 per cent

On a property built 1945 to 1979, that is about £5,438 set aside and not spent on anything you can see. Asbestos is very likely. Artex ceilings, garage roofs and floor tiles are the usual places.

The commonest budgeting mistake is leaving this out entirely. A contingency is not optional spending, it is spending you have not identified yet. If you finish without using it, you have a kitchen island. If you never had it, you have a half finished job and a difficult conversation.

Send the same document to every builder

Three quotes written to three different assumptions cannot be compared, which is how people end up picking the one that quietly left things out. This produces a scope with the same questions for everybody, including whether VAT is in the number and what happens if the scaffold stays up longer than planned.

Then keep hold of it once the work starts

The commonest cause of a dispute with a builder is not late payment. It is work that changed partway through and was never written down. Forty eight per cent of contractors who have payment disputes name unforeseen cost and scope change as the trigger, ahead of clients who will not pay.

Both sides remember the conversation differently six weeks later. Whoever wrote it down at the time is the one who is right.

A variation log
Every change recorded with the date, what it is, what it costs and who agreed it. Printable at the end as a single document.
Quote comparison
Put three quotes side by side on what each includes rather than what each totals. The cheapest number is rarely the cheapest job.
Budget tracking
Planned against actual by line, with the contingency drawn down separately so you can see how much of it is left.
Unlock for £29One payment, for the whole project. Refundable within fourteen days.
This is what we do for businesses, pointed at a house

Most of our work is tracking money that leaves in ways nobody wrote down at the start. A renovation turns out to be the same problem in a different costume. There are more free tools for homeowners, and rather more for businesses.

More for homeownersOr the business tools

Built by Lexalytic. See our other free tools.

Cost ranges are indicative figures drawn from published UK guides for 2026, which disagree with each other considerably. A kitchen is quoted anywhere between five and eighty five thousand pounds across sources depending on what is counted. Treat these as a starting point for a conversation rather than an estimate of your job, and get quotes from builders who have seen the property. This is not a quotation, a valuation or professional advice. Whether you need planning permission, building regulations approval or a party wall award depends on your specific property, and those should be confirmed with your council, an approved inspector or a surveyor rather than with a calculator.

Questions

What costs are not included in a builder quote?

VAT is the biggest and the most commonly missed, since a quote may be shown excluding it. Then contingency, architect or designer fees at five to twelve per cent of build cost, structural engineer calculations, Building Control fees, planning application fees, a party wall surveyor where work affects a shared wall, asbestos survey on anything built before 2000, scaffold, skip and parking permits, and somewhere to live if the property is uninhabitable. Furnishing the finished result is regularly a five figure sum that nobody budgets for.

How much contingency should a renovation have?

Ten per cent on a property built after 2000, rising to around twenty per cent on anything from before 1919. Older properties hide more: joists, wiring, damp, drainage and lath and plaster that cannot simply be skimmed over. The commonest budgeting mistake is leaving contingency out entirely, which does not remove the cost, only the plan for meeting it.

Why are renovation cost estimates so different between websites?

Because they count different things. A kitchen is quoted anywhere between five and eighty five thousand pounds across published UK guides, depending on whether the figure includes appliances, worktops, electrics behind the units, flooring, plastering and fitting, and on the specification assumed. Any single number is meaningless without knowing what sits inside it, which is why comparing quotes on inclusions rather than totals matters more than comparing calculators.

Do I need a party wall surveyor?

Potentially, where work affects a shared wall, involves excavation near a neighbouring property, or cuts into a party structure. You serve notice and the neighbour may consent or dissent. If they dissent, you generally pay for their surveyor as well as your own, so budget for two at one to three thousand pounds each. Serving notice early and properly is the cheapest way to stop this escalating. Whether it applies to your specific job should be confirmed with a surveyor.